New Ivy Transfer Station

Operations at Ivy MUC

Construction of New Transfer Station Begins

Construction of the new Transfer Station will begin in mid to late October as the building contractor, Lantz Construction Company (Lantz) of Broadway, Virginia, begins clearing the site and constructing storm water controls. The construction project will continue through the winter and is expected to be completed by the late fall of 2018.

Neighbors to the Ivy Material Utilization Center (Ivy MUC) may notice some intermittent additional truck traffic along portions of Dick Woods Road as concrete and building materials are delivered to the site. The contractor is expected to work normal daylight hours, Monday through Friday. There is no blasting planned for the project. Now that we are entering autumn and the leaves have begun falling from the trees, some of the construction work will be visible along the north side of Dick Woods Road (just to the west of the site entrance). Once complete, we expect that the remaining woodlands and planted visual buffers will screen much of the new facility.

Please check back here to stay abreast of updates on this project.

Timeline

  • Preliminary design completed January 2017.
  • Accepted construction bids August 3rd, 2017.
  • Received approval for Albemarle County site plan and water protection ordinance permit August 8, 2017.
  • Board approval of construction award September 2017.
  • Construction begins November 2017.
  • Project completion December 2018.

Additional Information

See floor plan and proposed traffic flow below: